From new intake to construction
Each project can span a different time period based on a number of different factors. Ideally, assuming all project details are valid, permits are approved and responses are quick, we aim to complete projects in 28 weeks.
The ideal timeline to submit a project is 28-52 weeks prior to anticipated occupancy date. It is important to keep TELUS up-to-date with all updates to occupancy dates.
Below you will see the phases, deliverables for each phase and ideal timelines for all projects phases:
Project Success Likelihood when project enters each phase | ||||
TELUS Build Phase | Main Deliverables |
On track Timeline (Ideal scenario) |
At risk Timeline | Low Priority Timeline |
New |
|
28-52 Weeks from Occupancy Date | < 28 weeks from Occupancy Date |
> 1 Year from Occupancy Date |
Planning Assessment |
|
24-52 Weeks from Build Ready Date | < 24 weeks from Build Ready Date | > 1 Year from Build Ready Date |
Design in Progress |
|
16-24 weeks from Build Ready Date | <16 weeks from Build Ready Date | > 24 weeks from Build Ready Date |
Construction |
|
8-24 weeks from Build Ready Date | <8 weeks from Build Ready Date | > 24 weeks from Build Ready Date |
Complete |
|
4-12 weeks from Occupancy Date | <4 weeks from Occupancy Date | > 12 weeks from Occupancy Date |